10 Installation Testing

Entry criteria: Before Installation Testing can take place the system must have undergone Function Testing, and be fully integrated.

Exit criteria: Installation of the system must be successful.

Installation Testing is conducted to verify that the software can be installed on the hardware/software platform specified in the SRS. Test cases for Installation Testing will follow through the procedure in the installation manual to install the software. As such, Installation Testing will also validate the installation guide.

If possible, Installation Testing will also take place on a machine matching the minimum hardware and software requirements criteria in the SRS.